A programme is judged on what arrives in your inbox, not what was promised in a meeting. These are the four documents that carry a luggage programme, shown here as sample formats so you can see the fields, the depth and the level of evidence behind each one.

How to read this page

Sample formats, not client documents

The figures, factory references and dates below come from a representative programme. Nothing on this page is a client document, and no client is named. Every live programme produces its own versions of these four documents, carrying your SKUs, your specification and your data — and each one is shared with you as it is produced, not assembled at the end.

Sample 01

Factory Evaluation Summary

What you receive after a factory visit: the scorecard, the findings that matter, and the conditions attached to an approval.

Evaluation referenceFE-2026-0311
Date of visit11 March 2026
FactoryFactory A — Dongguan, Guangdong
Category assessedHardside carry-on, 20in, 4-wheel
Visit typeAnnounced, full-day floor walk
Evaluated byLuggagePro programme team

Executive summary

  • Capability matches the brief: hardside moulding, wheel assembly and lining are in-house, with capacity headroom for the planned first run.
  • Quality system is present but uneven — incoming material inspection is documented, in-process checks are not.
  • Gauge calibration was 15 days overdue at the time of the visit; a corrective action was agreed with a date.
  • Compliance documents are current for the destination market, but wheel assembly subcontracting was confirmed verbally on site rather than declared in the questionnaire.
  • Two of the three lines that would run this product were at high load during the visit. Peak-season planning required.

Scorecard

CategoryFindingStatus
Production capacityMoulding and assembly in-house; 2 of 3 lines at high load during the visitAcceptable with peak-season planning
Quality systemIncoming and final inspection in place; in-process checks not recordedConditional — corrective action required
Compliance & documentationLicence, export record and test reports available; subcontracting not fully declaredFurther verification required
Supply chain stabilityWheel assembly partially subcontracted; two hardware items single-sourcedMonitor — dual-source before second run

Findings and disposition

FindingSeverityDisposition
Gauge calibration overdue by 15 daysMajorCorrective action agreed with a date; to be verified before sampling
Wheel assembly subcontracting not declared in advanceMajorDeclared on site; written confirmation requested
In-process inspection not recordedMinorRecord format agreed; first-article check to include written record

Recommendation: approved with conditions. Sampling may proceed once the calibration corrective action is verified. The two single-sourced hardware items should be dual-sourced before the second production run.

Sample 02

Pre-Shipment Inspection Report

The report that stands between a finished lot and your payment. Sampled to a stated AQL, with every finding photographed and counted.

Report numberPSI-2026-0417
Brand / programmeBrand X — carry-on range, first run
Supplier / factoryFactory A — Dongguan, Guangdong
Purchase orderPO-2026-0417
Product20in hardside carry-on, 4-wheel, 4 colourways
Order quantity (lot size)2,400 units
Inspection date17 April 2026
InspectorLuggagePro QC — inspector reference LP-04

Sampling plan

ItemBasis applied
StandardANSI/ASQ Z1.4 (ISO 2859-1)
Sampling planSingle, normal
Inspection levelGeneral II
AQL appliedCritical 0.0 / Major 1.5 / Minor 4.0
Sample size125 units
Sample selectionRandom, selected by the inspector from packed cartons

Inspection sections

#SectionResultNotes
1Quantity and production statusPassProduction 100% complete; 92% packed at time of inspection
2Workmanship — appearance and functionWithin AQL2 major, 5 minor recorded — see defect summary
3Tests and special checksPassWheel roll and handle static load performed on 10 units
4Packing and cartonsPassCarton grade and drop test consistent with the specification
5Shipping marks and labellingPassMarks match approved artwork; barcode scan verified
6Product conformity to specificationPassDimensions within tolerance; colour within the agreed grade

Defect summary

Defect classFoundMaximum allowedResult
Critical00Pass
Major25Pass
Minor514Pass

Defect detail

RefDescriptionClassUnitsDisposition
D-01Trolley handle locking button sluggish on extensionMajor1Reworked on site, re-inspected
D-02Lining stitch run-off at internal dividerMajor1Reworked on site, re-inspected
D-03Light scuffing on shell corner, colourway 3Minor3Accepted as minor; logged
D-04Carton print slightly out of register, carton 41Minor2Accepted; noted for next print run

Conclusion: passed. The lot meets the agreed acceptance criteria under the sampling plan applied. Both major defects were reworked and re-inspected on site before packing. This inspection is a sampled assessment under ANSI/ASQ Z1.4 and does not certify every unit in the lot.

Sample 03

Defect Log & Corrective Action Record

A failure is not closed when it is fixed. It is closed when the same failure can no longer happen — and somebody has proved it.

Record referenceCAPA-2026-07
Raised fromFinal inspection, production run 2
SeverityMajor
OwnerFactory quality lead, with the LuggagePro programme team
Target closure30 days from raising

Problem statement

14 of 600 units in production run 2 failed the trolley handle locking test at final inspection on 9 May 2026 — the handle extended but did not lock positively in the upper position. All 14 were isolated before packing. The failure mode did not appear in sampling, nor in run 1.

Containment

ActionOwnerDateStatus
Isolate the 14 affected units from packed stockFactory QC9 MayDone
100% locking check on the balance of the runFactory QC9–10 MayDone
Hold cartons 18–24 pending analysisFactory QC9 MayReleased 12 May after check

Root cause analysis — 5 Whys

  • Why did the handle fail to lock? The locking pawl did not engage fully in the upper detent.
  • Why? The pawl spring was seated deeper than the drawing allows.
  • Why? The spring seating tool had been swapped for a spare that was not to the original dimension.
  • Why? The spare was made in-house without a drawing check, and no first-article approval was applied to tooling replacements.
  • Why? The changeover procedure does not classify an in-house spare as a change requiring first-article approval.

Root cause: the tooling replacement procedure does not require first-article approval for in-house made spares.
Contributing cause: the locking test is not part of the in-process check at the handle assembly station.

Corrective and preventive actions

#ActionTypeOwnerDueStatus
1Restore the spring seating tool and verify it against the drawingCorrectionMaintenance12 MayDone
2Re-check and re-inspect all 14 isolated unitsCorrectionFactory QC12 MayDone
3Amend the changeover procedure: in-house spares require first-article approvalCorrectiveProcess engineer30 MayDone
4Add a locking test to the in-process check at handle assemblyCorrectiveFactory QC5 JunIn progress
5Apply the same spare-tool rule to all tooling across all linesPreventiveMaintenance20 JunIn progress

Verification of effectiveness

MethodSuccess criteriaCheckedResult
Review first-article records for all tooling changes100% of changes have a signed first-article record30 days after action 3Pending
Locking test results across 3 consecutive runsZero locking failures at final inspection60 daysPending
Spot check in-process records at handle assemblyLocking test present and completed each shift60 daysPending

Closure: this record cannot be closed until all three verification criteria are met. The 100% locking check remains in place until closure.

Sample 04

Programme Stage Tracker

One page that answers the only question a brand ever asks mid-programme: where are we, and what has to be true before we move?

StageDeliverableGate criteriaStatus
1 Discovery & specWritten specification, target cost, compliance marketSpecification signed off; price target tested against factory quotesComplete
2 Factory matchEvaluation summary per factory, with comparisonFactory approved with conditions; corrective actions datedComplete
3 Sampling & validationSample evaluation report against the specificationSample passes every specification point; drop and wheel tests passedComplete
4 Pilot runPilot run report, first-article recordsPilot quantity within AQL; no critical defects; tooling approvedComplete
5 ProductionIQC / IPQC / FQC records, photo-documentedEach gate signed off; defect log currentIn progress — run 3
6 Pre-shipmentPre-shipment inspection report, defect logLot meets AQL; major defects closed or reworkedNot started
7 LogisticsDocuments set: invoice, packing list, test reportsDocuments match the order and destination requirementsNot started
8 After-salesWarranty parts plan, defect follow-up logSpare parts available; defect closure rates reportedNot started

Sample formats shown for illustration of structure and level of detail. Live documents carry programme-specific data and are issued during the programme, at the gate where they are produced.

Want to see these for your product?

Send us the brief and we will tell you which of these documents your programme would produce, and when.